Case study: kanban-kit – Business Application

Case study: kanban-kit

How we built a complete product with the KI-Leitstand – and how we measure what came out of it.

Our own project, not a client project.

Starting point

We wanted to know whether AI-assisted development can carry a real product and not just a prototype. For that we needed a tool ourselves: a Kanban board on which work is described, and a control centre that shows what the AI made of it. The result was kanban-kit – multi-tenant, self-hostable and open source, with Spring Boot and Postgres in the backend and React in the frontend.

How we worked with the KI-Leitstand

Every change starts as a card on the board: first as a business requirement, then as a plan, then as small work packages with acceptance criteria. The AI implements one package after another, often at night via a runner, and every package has to pass type checking, tests and the build before it goes to acceptance. A second model reviews the code, and we accept it before anything goes live. The KI-Leitstand shows every run with its outcome: green, yellow or red.

Results in numbers

As of: 24 November 2026

Lead time

1.9 days

Basis
1,724 cards
Method of measurement
Mean time from the creation of a card to Done across all completed cards.
Calculation of the lead time in the source code

Implementation time

15 minutes

Basis
1,248 cards
Method of measurement
Mean time a finished card spent in In Progress columns, rework included.
Calculation of the implementation time in the source code

Share of green runs

94%

Basis
last 711 packages (670 green, 10 yellow, 31 red)
Method of measurement
Green packages divided by green, yellow and red ones; skipped packages do not count.
Calculation of the share of green runs in the source code

The values are internal measurements; the method of measurement is publicly verifiable.

Key facts kanban-kit

Period
9 July to 24 November 2026
Commits
1,979
Releases
95
Test files
861

Counted on the reference date on the main branch: all commits since the first one, all version tags as releases, and as test files the files that are tests according to the project's naming pattern.

kanban-kit on GitHub

Excerpt from the KI-Leitstand of kanban-kit on 24 November 2026: three tiles with lead time 1.9 days across 1724 cards, implementation time 15 minutes across 1248 cards and runs green 94 percent with 670 green, 10 yellow and 31 red of the last 711 packages.
Screenshot of the Leitstand (German interface)

For comparison: this website

The following figures come from the project behind the website you are reading right now. It consists mostly of pages with a thin layer and no business logic, which is why its work packages are shorter than in kanban-kit. The figures from kanban-kit are closer to a client project. The shorter time of this website is not a promise for every application.

Lead time

0.7 days

Basis
155 cards
Method of measurement
Mean time from the creation of a card to Done across all completed cards.
Calculation of the lead time in the source code

Implementation time

4 minutes

Basis
93 cards
Method of measurement
Mean time a finished card spent in In Progress columns, rework included.
Calculation of the implementation time in the source code

Share of green runs

98%

Basis
last 94 packages (92 green, 0 yellow, 2 red)
Method of measurement
Green packages divided by green, yellow and red ones; skipped packages do not count.
Calculation of the share of green runs in the source code

Key facts of this website

Period
26 October to 24 November 2026
Commits
122
Test files
65

The counting rule above also applies to this website. Test files here are the files ending in .test.ts, .test.tsx and Test.php. Releases are not listed because the website has no version tags.

Excerpt from the KI-Leitstand of this website on 24 November 2026: three tiles with lead time 0.7 days across 155 cards, implementation time 4 minutes across 93 cards and runs green 98 percent with 92 green, 0 yellow and 2 red of the last 94 packages.
Screenshot of the Leitstand (German interface)

What we learned

Small packages beat big leaps: the more narrowly a card is cut, the more often it goes green on the first attempt. Red runs are no harm, they are the checks doing their job – they stop before anything wrong reaches the main branch. Tests alone are not enough; only mutation tests showed which tests really check something. And the decisions stay with us: the AI builds what is on the card, and we accept what goes live.

The tool itself: claude-workflow-kit

We built kanban-kit with the claude-workflow-kit, the set of rules, skills and checks that carries the process from the board to the commit. The kit was itself built with itself and is therefore our second case.

Period
29 June to 24 November 2026
Commits
2,217
Releases
71
Test files
840

The development repository is private; the community edition is public.

Community edition of the claude-workflow-kit on GitHub

How our software factory works with the claude-workflow-kit (PDF, 13 pages) (German)